Project Update

Project Name:  Hopkins Street Improvements - Bishop to Moore

Current Update: 03/2021

Work Completed Last Month: Concrete intersection at Mitchell and second lift of asphalt were completed in Phase 1 (Johnson to Endicott). Phase 2 (Bishop to Johnson) waterline was completed and placed in service.

Work Planned This Month: Phase 2 Storm and Sanitary lines are expected to be completed in April. Preparation of roadway base will begin towards the end of April in Phase 2.

Construction Completion: See Dashboard

Pictures from last month
Phase 1 - Second lift of AsphaltPhase 2 - Water Tie inPhase 1 - Mitchell intersection Concrete and Pavers