Kingwood and Sherwood Improvements

Kingwood Street and Sherwood Drive are located in southwest San Marcos and connect to the TxDOT IH 35 frontage road. They are within the Willow Springs Creek watershed.  The project will reconstruct both streets, upgrade the existing water and wastewater systems, and construct a new street drainage system. The project will also evaluate sidewalks and stormwater quality treatment facilities.

The project will be conducted in the following phases:

Design Phase 1 

Started February 2020 - including topographic surveys

Preliminary Engineering Report (Draft) Submitted September 2020

Finalize Preliminary Engineering Report – October 2020

Design Phase 2 – 

Continue Designs – 2021 

Public Meeting – Early 2021

Complete Designs - 2022

Schedule and Budget

Construction start - Early 2023

Design - $400,000

Construction - $2,500,000

Kingwood Sherwood Location Map