Midway Utility Improvements

Midway Street Area Project Map - includes Perkins, Midway, Alto and Waco

This project will provide the following:

  • Addition of wastewater infrastructure along part of Perkins St. and Midway St. to provide wastewater service to future affordable housing units on the site of the former Midway water storage facility. 
  • Provide sewer infrastructure to allow for existing properties on Perkins St. and Midway St. on septic systems to move onto the system collection system in the future 
  • Improvements and extensions of sewer and water lines along Waco St. 

Project Status and Schedule

  •  Design is at 90 Percent Stage. 
  • Construction is scheduled for FY 2022 at an estimated cost of $1M