Project Update - August 2018 


As of August 12, the following is the schedule of construction: 

  • MLK and Armstead Streets will be have asphalt pavement laid within a week
  • Travis Street box culvert construction will be complete within two weeks
  • Upon completion of the work on Travis Street the contractor will begin road repairs and restoration – estimated duration of 6 weeks
  • Once MLK is restored and reopened San Antonio Street will be closed, ~ 1 week
  • San Antonio Street construction will consist of the completion of water and wastewater work and installation of box culverts from Armstead to Travis Street – estimate duration 8 weeks
  • All construction time estimates are weather dependent.