Project Update - October 2019

Phase Two Traffic Control Plan in Effect September 5, 2019  (PDF)


Southbound lane along Mill Street and westbound lane along Uhland Road will be closed for this roadway and drainage improvement project. Phase One lane closures are expected to continue until September 4, 2019.

On September 5, 2019, phase 2 traffic control plan will be placed; northbound lane along Mill Street and eastbound lane along Uhland Road will be closed for roadway and drainage improvements. The traffic will be diverted to the newly constructed road so that the construction can start on the east side of Mill St. Please see phase 2 traffic control plan.

Motorists should use caution in construction areas and follow detour signs

Waterline and storm drain has been installed. Subgrade, flex base, asphalt, curb and gutter and sidewalk work on the west side of Mill St and on the north side of Uhland Road is complete. Roadway construction on the east side of Mill St and on the south side of Uhland Road will start on September 5, 2019.

Expected timeline to complete asphalt along Mill Street is late 2019