Project Update - January 2020

  • Excavation and demolition on Roosevelt between Guadalupe and McArthur began last Monday (1/6/20).
  • The contractor was able to excavate to subgrade, proof roll and pass density testing prior to installing road base. Rain has prevented processing of the base to achieve a stable, compacted surface for driving.
  • Excavation and demolition began on Roosevelt between McArthur and Churchill on Monday 1/13/20. Residents were given door to door notification by the contractor.
  • City sent out notification to the entire neighborhood by mail of the construction activities anticipated during the month of January (see below). This update also contained an update of all utility and roadwork that has been installed and that is remaining.
  • Prior to starting excavation on the next phase of Roosevelt the contractor will continue to give door to door notification followed by monthly City project updates.
January Monthly Construction Update 1
January Monthly Construction Update 2

We’re here if you need us: 

After hours - David VanDyke, Cox Construction - 512.618.2249

Damage claims - Cindy Conyers, City of San Marcos - 512.393.8065

Towing issues/expenses - Rey Garcia, City of San Marcos - 512.393.8143

General questions, concerns - Nancy Hyde, City of San Marcos - 512.393.8130