Project Update - February 2019

  • Wastewater line installation continues on Roosevelt Street west of Patton, and on Armstrong 
  • Wastewater installation will begin next on Railroad, Armstrong, Churchill then continue to Patton
  • By the end of February wastewater installation in the east side of the subdivision should be complete, weather permitting. Crews will then begin waterline installation in the same areas