Project Update - October 2019

As of September 30th:

  • Installation of first layer of asphalt is complete. There are two more layers to go.
  • Concrete curbing is 90% installed.
  • Concrete sidewalks are 65% complete
  • Drainage infrastructure installation is 97% complete.
  • Concrete driveway installation is 80% complete.
  • Foundation installation for pedestrian lighting and traffic signals is complete.
  • Crosswalk at Hopkins is open and operational with functioning pedestrian signals.

The following progress is expected to be made during the month of October:

  • Complete concrete curbing and driveway installation.
  • Complete 95% of concrete sidewalk installation.
  • Complete 50% of concrete median work.
  • Complete LID features.
  • Begin construction on biofiltration pond.

We expect the project to be substantially complete just prior to Sights and Sounds. We expect to open the road to traffic once Sights and Sounds has concluded.