Bishop Street Improvements - August 2019

This project includes a full depth road reconstruction with drainage, water, wastewater, retaining walls and sidewalk improvements. The design is approximately 25% complete at this time. Engineers are evaluating the addition of a water quality pond near the outfall at Purgatory Creek, as well as expanding the project limits to capture runoff coming down Veramendi Street. A public meeting will be held in 2020 after the project scope is finalized.

o    Construction Cost - $6.0M                  o    Construction Start -  2021


Bishop Street Overall Project View

Bishop St Improvements Overall Exhibit