Project Update - September 2018

The second phase of construction started after Labor Day. 

The bore under the San Marcos River is almost complete. The contractor will begin pulling the new pipe under the river by the end of the week of September 24th. 

Once the bore is complete it will be connected to existing waterlines on both sides of the river.

The project should be complete by the end of October, weather permitting.


20180927 Cheatham Water Line