Reclaimed Water System Expansion - September 2020

Storage tank is complete

  • Contractor is working on pre-punch list items
  • SCADA programming is in progress
  • SCADA system will communicate with Reclaimed Water Pump Station to gather and analyze data in real time

Pump Station Improvements Project

  • All three pumps have been removed and replaced
  • System acceptance testing in September 2020